1) All floor tiles and kitchen wall tiles have been done.
2) Wooden flooring done on Friday, 25 Sep 2009.
3) All carpentry work is fabricating in the workshop now.
4) 1st coat of paint done. (Color code: Nippon Urban grey)
5) 1st chemical wash done.
Need to rectify
1) Bathroom piping need to be shifted near to center.
2) False wall need to erect.
Yet to be done
1) Aircon and lightings need to be installed.
2) Wall-hung water closet need to be setup.
3) New rubbish chute to be installed.
4) Bathroom accessories need to setup.
5) Sockets and switches.
6) Door and mild steel gate.
7) Pebbles floor
8) Carpentry work.
9) Glass panel for bedroom, sliding doors and fixed panel.
10) Fabrication of Solid surface top.
11) Installation of digital lock.
12) Side latches (headboard) for both ends.
13) Light box @patio area.
14) Wardrobe mirror with leather framing,